Corona Golf Playground Pavement Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct pavements at Corona Golf Playground.
Project Timeline
Design
Start Date: September 2019
Projected Completion Date:
May 2020
Completion Date:
March 2020
Procurement
Start Date: September 2019
Projected Completion Date:
February 2020
Completion
Date:
February 2020
Construction
Start Date: March 2020
Projected Completion Date:
July 2020
Completion
Date:
May 2020