McKinley Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    55% complete

This project will reconstruct the comfort station in McKinley Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: August 2019
Projected Completion Date: February 2020
Completion Date: February 2020

Procurement

Start Date: September 2019
Projected Completion Date: February 2020
Completion Date: February 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $911,000
Funding Source: Mayoral

Location

McKinley Playground , Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 05/07/2021