Little Flower Playground Synthetic Turf Field Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a synthetic turf field at Little Flower Playground.
Project Timeline
Design
Start Date: April 2019
Projected Completion Date:
December 2019
Completion Date:
December 2019
Procurement
Start Date: July 2019
Projected Completion Date:
December 2019
Completion
Date:
November 2019
Construction
Start Date: March 2020
Projected Completion Date:
June 2020
Completion
Date:
September 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Little Flower Playground
, Manhattan
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/15/2021