Little Flower Playground Synthetic Turf Field Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    90% complete

This project will construct a synthetic turf field at Little Flower Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2019
Projected Completion Date: December 2019
Completion Date: December 2019

Procurement

Start Date: July 2019
Projected Completion Date: December 2019
Completion Date: December 2019

Construction

Start Date: March 2020
Projected Completion Date: June 2020
Adjusted Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $531,000
Funding Source: Mayoral

Location

Little Flower Playground , Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/07/2020