Highbridge Park Step Street Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    41% complete

This project will restore the step street and surrounding landscape in Highbridge Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: August 2011
Projected Completion Date: June 2015
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: January 2020

Construction

Start Date: March 2020
Projected Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $6,700,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council
  • Federal

Location

Highbridge Park , Bronx
West 170th Street between University Avenue and Sedgwick Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/19/2020