Sara D. Roosevelt Park Comfort Station and Communications Office Building Reconstruction

  • Design
    30% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the comfort station and communications office building in Sara D Roosevelt Park.

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

NYC Parks has received budget approval and is finalizing the work order documentation.

Project Timeline

Design

Start Date: November 2018
Projected Completion Date: September 2019

Procurement

Start Date: May 2019
Projected Completion Date: October 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Sara D. Roosevelt Park , Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 09/19/2019