Grant Park Playground and Basketball Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground and basketball court at Grant Park.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: December 2016
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: May 2018
Completion Date: July 2018

Construction

Start Date: August 2018
Projected Completion Date: February 2020
Completion Date: March 2020

Understand how we build parks.

Funding

Total Funding: $3,255,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Grant Park , Bronx
Grant Avenue and East 169th Street

 

Project Staff

Project Liaison: Mike Ortiz
Contact NYC Parks about this project

Last updated: 08/15/2022

Was this information helpful?