Kolbert Park Sidewalks Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the sidewalks, curbs, accessible ramps, and pipe rail fencing at Kolbert Playground.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: January 2019
Projected Completion Date: May 2019
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: October 2019
Completion Date: July 2019

Construction

Start Date: November 2019
Projected Completion Date: May 2020

Understand how we build parks.

Funding

Total Funding: $364,000
Funding Source: City Council

Location

Kolbert Playground , Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/13/2020