Kolbert Park Sidewalks Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the sidewalks, curbs, accessible ramps, and pipe rail fencing at Kolbert Playground.

Project Timeline

Design

Start Date: January 2019
Projected Completion Date: May 2019
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: October 2019
Completion Date: July 2019

Construction

Start Date: November 2019
Projected Completion Date: May 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $364,000
Funding Source: City Council

Location

Kolbert Playground , Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/28/2020