Hooper Grove Community Garden Fence Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct new steel fences with concrete curbs and install water service at Hooper Grove Community Garden.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: March 2019
Projected Completion Date: May 2019
Completion Date: April 2019

Procurement

Start Date: May 2019
Projected Completion Date: October 2019
Completion Date: July 2019

Construction

Start Date: October 2019
Projected Completion Date: February 2020

Understand how we build parks.

Funding

Total Funding: $26,000
Funding Source: City Council

Location

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 12/12/2019