Frederick Douglass Boulevard Community Garden Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Frederick Douglass Boulevard Community Garden with new pavements and plantings.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: May 2018
Projected Completion Date: May 2019
Completion Date: August 2019

Procurement

Start Date: March 2019
Projected Completion Date: August 2019
Completion Date: August 2019

Construction

Start Date: October 2020
Projected Completion Date: April 2021

Understand how we build parks.

Funding

Total Funding: $107,000
Funding Source: Borough President

Location

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/19/2020