Estella Diggs Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct additional fencing, paths, seating and miscellaneous site amenities at Rocks & Roots Park (Estella Diggs).

Project Timeline


Start Date: October 2012
Projected Completion Date: June 2014
Completion Date: October 2014


Start Date: October 2014
Projected Completion Date: July 2015
Completion Date: July 2015


Start Date: October 2015
Projected Completion Date: October 2016
Completion Date: May 2017

Understand how we build parks.


Total Funding: $1,547,000
Funding Sources:
  • Borough President
  • City Council


Estella Diggs Park , Bronx
East 167th Street between Third and Fulton Avenues


Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 03/21/2018