NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Estella Diggs Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct additional fencing, paths, seating and miscellaneous site amenities at Rocks & Roots Park (Estella Diggs).

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: October 2012
Projected Completion Date: June 2014
Completion Date: October 2014

Procurement

Start Date: October 2014
Projected Completion Date: July 2015
Completion Date: July 2015

Construction

Start Date: October 2015
Projected Completion Date: October 2016
Completion Date: May 2017

Understand how we build parks.

Funding

Total Funding: $1,461,000
Funding Sources:
  • Borough President
  • City Council

Location

Estella Diggs Park, Bronx
East 167th Street between Third and Fulton Avenues

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/14/2017