John Finley Walk 82nd Street ADA Ramp Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct a masonry ramp to provide ADA access to John Finley Walk at East 82nd Street.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: August 2018
Projected Completion Date: August 2019
Completion Date: June 2019

Procurement

Start Date: October 2018
Projected Completion Date: March 2019
Completion Date: May 2019

Construction

Start Date: August 2019
Projected Completion Date: December 2019

Understand how we build parks.

Funding

Total Funding: $224,000
Funding Source: Mayoral

Location

East River Walk , Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/20/2019