Kelly Playground Skate Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    67% complete

This project will construct a skate park and reconstruct the amphitheater and basketball courts in Kelly Playground (PS 52).

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2011
Projected Completion Date: November 2013
Completion Date: April 2015

Procurement

Start Date: April 2015
Projected Completion Date: January 2016
Completion Date: April 2016

Construction

Start Date: May 2016
Projected Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $2,658,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Playground 52 LII, Bronx
Avenue Saint John between Kelly and Beck Streets

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 02/16/2018