Dekovats Playground Safety Surfacing Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the safety surfacing at Dekovats Playground.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: February 2018
Projected Completion Date: December 2018
Completion Date: November 2018

Procurement

Start Date: June 2018
Projected Completion Date: November 2018
Completion Date: November 2018

Construction

Start Date: December 2018
Projected Completion Date: February 2019

Understand how we build parks.

Funding

Total Funding: $231,000
Funding Source: Mayoral

Location

Asphalt Green , Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 12/15/2018