Red Hook Pool Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct various areas of the pool tub and expansion joints at Red Hook Pool.

Project Timeline

Design

Start Date: January 2018
Projected Completion Date: December 2017
Completion Date: July 2018

Procurement

Start Date: March 2018
Projected Completion Date: August 2018
Completion Date: July 2018

Construction

Start Date: September 2018
Projected Completion Date: October 2018
Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $109,000
Funding Source: Mayoral

Location

Red Hook Recreation Area , Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 07/22/2019