Clove Lake Park Parking Lot Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct concrete curbs in the parking lot, add accessible ramp, and repair drainage problems in the parking lot and at the comfort station.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: July 2018

Procurement

Start Date: February 2018
Projected Completion Date: July 2018
Completion Date: July 2018

Construction

Start Date: August 2018
Projected Completion Date: November 2018

Understand how we build parks.

Funding

Total Funding: $108,000
Funding Source: Mayoral

Location

Clove Lakes Park , Staten Island

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 10/22/2018