Van Cortlandt Park Pool Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the pool deck at the Van Cortlandt Park pool.

Project Timeline

Design

Start Date: July 2017
Projected Completion Date: July 2017
Completion Date: November 2017

Procurement

Start Date: October 2017
Projected Completion Date: March 2018
Completion Date: November 2017

Construction

Start Date: November 2017
Projected Completion Date: December 2017
Completion Date: June 2016