Orchard Beach Nature Center Roof Replacement

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will replace the roof at Orchard Beach Nature Center.

Project Update: A date has been set for construction to begin.

Project Timeline


Start Date: April 2017
Projected Completion Date: July 2017
Completion Date: November 2017


Start Date: August 2017
Projected Completion Date: January 2018
Completion Date: October 2017


Start Date:

Understand how we build parks.


Total Funding: $208,000
Funding Source:


Pelham Bay Park , Bronx


Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 03/16/2018