Forest Park Sobelsohn Playground Comfort Station Electrical System Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the comfort station electrical system at Sobelsohn Playground in Forest Park.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: May 2017
Completion Date: November 2017

Procurement

Start Date: August 2017
Projected Completion Date: January 2018
Completion Date: October 2017

Construction

Start Date:

Understand how we build parks.

Funding

Total Funding: $56,000
Funding Source: City Council

Location

Forest Park, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/20/2017