Forest Park Sobelsohn Playground Comfort Station Electrical System Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    85% complete

This project will reconstruct the comfort station electrical system at Sobelsohn Playground in Forest Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: May 2017
Completion Date: November 2017

Procurement

Start Date: August 2017
Projected Completion Date: January 2018
Completion Date: October 2017

Construction

Start Date: September 2019
Projected Completion Date: June 2020

Understand how we build parks.

Funding

Total Funding: $56,000
Funding Source: City Council

Location

Forest Park , Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 07/05/2020