Forest Park Sobelsohn Playground Comfort Station Plumbing System Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the comfort station plumbing system at Sobelsohn Playground in Forest Park.
Project Timeline
Design
Start Date: November 2016
Projected Completion Date:
May 2017
Completion Date:
November 2017
Procurement
Start Date: August 2017
Projected Completion Date:
January 2018
Completion
Date:
October 2017
Construction
Start Date: September 2019
Projected Completion Date:
June 2020
Completion
Date:
September 2020
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Forest Park
, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 08/17/2022