Harry Chapin Playground Sprinkler Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install a new drainage line and hydraulic board activator at Harry Chapin Playground.

Project Timeline

Design

Start Date: May 2017
Projected Completion Date: June 2018
Completion Date: September 2018

Procurement

Start Date: March 2018
Projected Completion Date: August 2018
Completion Date: September 2018

Construction

Start Date: August 2019
Projected Completion Date: October 2019
Completion Date: November 2019

Understand how we build parks.

Funding

Total Funding: $88,000
Funding Sources:
  • Mayoral
  • City Council

Location

Harry Chapin Playground , Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/15/2019