Harry Chapin Playground Sprinkler Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will install a new drainage line and hydraulic board activator at Harry Chapin Playground.
Project Timeline
Design
Start Date: May 2017
Projected Completion Date:
June 2018
Completion Date:
September 2018
Procurement
Start Date: March 2018
Projected Completion Date:
August 2018
Completion
Date:
September 2018
Construction
Start Date: August 2019
Projected Completion Date:
October 2019
Completion
Date:
November 2019
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Harry Chapin Playground
, Brooklyn
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 08/11/2022