Sunset Park Spray Shower Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the subterranean controller vaults for the spray shower at Sunset Park.

Project Timeline

Design

Start Date: December 2015
Projected Completion Date: January 2016
Completion Date: June 2017

Procurement

Start Date: March 2017
Projected Completion Date: August 2017
Completion Date: April 2017

Construction

Start Date: March 2018
Projected Completion Date: June 2018
Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $170,000
Funding Source: Mayoral