Sunset Park Spray Shower Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the spray shower subterranean controller vaults.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: December 2015
Projected Completion Date: January 2016
Completion Date: June 2017

Procurement

Start Date: March 2017
Projected Completion Date: August 2017
Completion Date: April 2017

Construction

Start Date: November 2017
Projected Completion Date: March 2018

Understand how we build parks.

Funding

Total Funding: $170,000
Funding Source: Mayoral

Location

Sunset Park , Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 04/24/2018