Mullaly Recreation Center Door Replacement

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will install new entrance doors at Mullaly Recreation Center.

Project Update: NYC Parks staff members are currently reviewing the scope of the work order.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: January 2017
Completion Date: March 2017

Procurement

Start Date: August 2017
Projected Completion Date: January 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: $185,000
Funding Sources:
  • Mayoral
  • City Council

Location

Mullaly Park, Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/20/2017