Mullaly Recreation Center Door Replacement

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install new entrance doors at Mullaly Recreation Center.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: January 2017
Completion Date: March 2017

Procurement

Start Date: August 2017
Projected Completion Date: January 2018
Completion Date: February 2018

Construction

Start Date: February 2018
Projected Completion Date: March 2018
Completion Date: March 2018

Understand how we build parks.

Funding

Total Funding: $97,000
Funding Sources:
  • Mayoral
  • City Council

Location

Mullaly Park , Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 08/20/2018