Conference House Beach Temporary Berm Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct temporary berms installed after Hurricane Sandy at Conference House Beach in Staten Island.

Project Timeline

Design

Start Date: November 2014
Projected Completion Date: June 2015
Completion Date: February 2016

Procurement

Start Date: March 2016
Projected Completion Date: August 2016
Completion Date: February 2016

Construction

Start Date: July 2016
Projected Completion Date: August 2016
Completion Date: August 2016

Understand how we build parks.

Funding

Total Funding: $168,000
Funding Source: Mayoral

Location

Conference House Park , Staten Island

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/27/2020