Skyline Playground Tennis Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the tennis courts at Skyline Playground.

Project Timeline

Design

Start Date: September 2016
Projected Completion Date: November 2016
Completion Date: December 2016

Procurement

Start Date: September 2016
Projected Completion Date: February 2017
Completion Date: March 2017

Construction

Start Date: March 2017
Projected Completion Date: March 2019
Completion Date: July 2017

Understand how we build parks.

Funding

Total Funding: $275,000
Funding Sources:
  • Mayoral
  • Federal

Location

Skyline Playground , Staten Island

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 08/17/2018