NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Fresh Kills Park Zink House Roof Replacement

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will replace the roof at Fresh Kills Park Zink House.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: May 2016
Projected Completion Date: July 2016
Completion Date: November 2016

Procurement

Start Date: August 2016
Projected Completion Date: January 2017
Completion Date: November 2016

Construction

Start Date: December 2016
Projected Completion Date: September 2017

Understand how we build parks.

Funding

Total Funding: $60,000
Funding Source: Mayoral

Location

Freshkills Park, Staten Island

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 09/21/2017

Was this information helpful?