Fort Totten Building 429 Roof Replacement

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will replace the roof at Fort Totten Building 429.

Project Timeline

Design

Start Date: May 2016
Projected Completion Date: July 2016
Completion Date: November 2016

Procurement

Start Date: August 2016
Projected Completion Date: January 2017
Completion Date: November 2016

Construction

Start Date: December 2016
Projected Completion Date: February 2017
Completion Date: February 2017

Understand how we build parks.

Funding

Total Funding: $227,000
Funding Source: Mayoral

Location

Fort Totten Park, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/20/2017