Zimmerman Playground Comfort Station Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roof at the comfort station in Zimmerman Playground.

Project Timeline

Design

Start Date: May 2016
Projected Completion Date: July 2016
Completion Date: November 2016

Procurement

Start Date: August 2016
Projected Completion Date: January 2017
Completion Date: November 2016

Construction

Start Date: December 2016
Projected Completion Date: April 2017
Completion Date: April 2017

Understand how we build parks.

Funding

Total Funding: $76,000
Funding Source: Mayoral

Location

Zimmerman Playground , Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 08/12/2022