Zimmerman Playground Comfort Station Roof Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the roof at the comfort station in Zimmerman Playground.
Project Timeline
Design
Start Date: May 2016
Projected Completion Date:
July 2016
Completion Date:
November 2016
Procurement
Start Date: August 2016
Projected Completion Date:
January 2017
Completion
Date:
November 2016
Construction
Start Date: December 2016
Projected Completion Date:
April 2017
Completion
Date:
April 2017
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Zimmerman Playground
, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 08/12/2022