Sunset Park Playground Reconstruction

  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    23% complete 

This project will reconstruct the playground in Sunset Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2011
Projected Completion Date:December 2012
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date:September 2014
Completion Date: October 2015

Construction

Start Date: April 2016
Projected Completion Date:April 2017

Understand how we build parks.

Funding

Total Funding: $2,924,000
Funding Sources:
  • Mayor
  • City Council
Design of Sunset Park Playground Reconstruction

Location

Sunset Park, Brooklyn
Sixth Avenue at 44th Street, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/24/2017