Sunset Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground in Sunset Park.

Project Timeline


Start Date: October 2011
Projected Completion Date: December 2012
Completion Date: December 2013


Start Date: December 2013
Projected Completion Date: September 2014
Completion Date: October 2015


Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: July 2017

Understand how we build parks.


Total Funding: $3,103,000
Funding Sources:
  • Mayoral
  • City Council


Sunset Park , Brooklyn
Sixth Avenue at 44th Street, Brooklyn


Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 03/23/2018