NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Sunset Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    65% complete

This project will reconstruct the playground in Sunset Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: October 2011
Projected Completion Date: December 2012
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: September 2014
Completion Date: October 2015

Construction

Start Date: April 2016
Projected Completion Date: April 2017
Adjusted Completion Date: July 2017

Understand how we build parks.

Funding

Total Funding: $2,924,000
Funding Sources:
  • Mayoral
  • City Council

Location

Sunset Park, Brooklyn
Sixth Avenue at 44th Street, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/21/2017

Was this information helpful?