Gateway Estates Phase 1 Playground and Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a playground and comfort station at Gateway Estates.

Project Timeline

Design

Start Date: July 2011
Projected Completion Date: October 2013
Completion Date: March 2015

Procurement

Start Date: March 2015
Projected Completion Date: December 2015
Completion Date: March 2016

Construction

Start Date: September 2016
Projected Completion Date: March 2019
Completion Date: February 2019

Understand how we build parks.

Funding

Total Funding: $4,914,000
Funding Source: Mayoral

Location

Vandalia Avenue and Berriman Street, Erskine Street and Schroeders Avenue

Related Projects

Total Funding for These Related Projects: Between $3 million and $10 million
Funding Source: Mayoral

Project Phase
Gateway Estates Phase 1 Playground and Comfort Station Construction - Electrical Completed
Gateway Estates Phase 1 Playground and Comfort Station Construction - HVAC Completed
Gateway Estates Phase 1 Playground and Comfort Station Construction - Plumbing Completed

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 04/24/2019