Cadman Plaza Park Brooklyn War Memorial ADA Ramp and Elevator Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will install an accessible ramp and elevator at the Brooklyn War Memorial in Cadman Plaza Park.

Project Update: The contract is registered.

Project Timeline

Design

Start Date: June 2016
Projected Completion Date: June 2017
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: May 2018
Completion Date: July 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council
  • Federal

Location

Cadman Plaza Park , Brooklyn
Cadman Plaza West, Tillary Street, Cadman Plaza East, Tillary Street, Brooklyn Bridge

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/16/2019