Thomas Greene Playground Pool Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the concrete pool deck at Thomas Greene Playground.

Project Timeline

Design

Start Date: January 2016
Projected Completion Date: March 2016
Completion Date: September 2016

Procurement

Start Date: April 2016
Projected Completion Date: September 2016
Completion Date: September 2016

Construction

Start Date: December 2016
Projected Completion Date: June 2017
Completion Date: June 2017

Understand how we build parks.

Funding

Total Funding: $55,000
Funding Source: Mayoral

Location

Thomas Greene Playground , Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 09/19/2019