Staten Island General Site Work (RG-212M)

  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    100% complete 

This project will reconstruct paving, safety surfacing, play equipment and sitework.

Project Timeline

Design

Start Date: April 2012
Projected Completion Date:May 2012
Completion Date: July 2013

Procurement

Start Date: July 2013
Projected Completion Date:April 2014
CompletionDate: July 2014

Construction

Start Date: February 2015
Projected Completion Date:February 2017
CompletionDate: December 2016

Understand how we build parks.

Funding

Total Funding: $2,000,000
Funding Source:Mayor

Location

Various locations, Staten Island

Project Staff

Project Liaison: Charles Fall