Calvert Vaux Park Comfort Station and Maintenance Facility Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    75% complete

This project will construct a comfort station and maintenance facility in Calvert Vaux Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: July 2011
Projected Completion Date: August 2014
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: July 2019

Construction

Start Date: December 2019
Projected Completion Date: May 2021
Adjusted Completion Date: July 2022

Understand how we build parks.

Funding

Total Funding: $10,162,000
Funding Sources:
  • Mayoral
  • City Council

Location

Calvert Vaux Park , Brooklyn
Shore Parkway near Bay 48th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 05/17/2022

Was this information helpful?