Calvert Vaux Park Comfort Station and Maintenance Facility Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct a comfort station and maintenance facility in Calvert Vaux Park.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: July 2011
Projected Completion Date: August 2014
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: July 2019

Construction

Start Date: October 2019
Projected Completion Date: April 2021

Understand how we build parks.

Funding

Total Funding: $10,163,000
Funding Sources:
  • Mayoral
  • City Council

Location

Calvert Vaux Park , Brooklyn
Shore Parkway near Bay 48th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 09/20/2019