Flushing Meadows Corona Park Pool Locker Room Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the men's locker room in the FMCP pool facility into a family changing room.

Project Timeline

Design

Start Date: January 2016
Projected Completion Date: March 2016
Completion Date: October 2016

Procurement

Start Date: April 2016
Projected Completion Date: September 2016
Completion Date: October 2016

Construction

Start Date: October 2016
Projected Completion Date: May 2017
Completion Date: October 2017

Understand how we build parks.

Funding

Total Funding: $145,000
Funding Sources:
  • Mayoral

Location

Flushing Meadows Corona Park, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/20/2017