Marine Park Bocce Court and Sport Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the bocce courts, sports courts and landscaping at Marine Park.

Project Timeline


Start Date: March 2012
Projected Completion Date: January 2014
Completion Date: January 2015


Start Date: January 2015
Projected Completion Date: October 2015
Completion Date: July 2015


Start Date: October 2015
Projected Completion Date: March 2017
Completion Date: December 2016

Understand how we build parks.


Total Funding: $5,454,000
Funding Source: City Council


Marine Park , Brooklyn
Located on the corner of Fillmore Avenue and East 32nd Street in Marine Park.