  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    100% complete 

This project will reconstruct the bocce courts, sports courts and landscaping at Marine Park.

Project Timeline

Design

Start Date: March 2012
Projected Completion Date:January 2014
Completion Date: January 2015

Procurement

Start Date: January 2015
Projected Completion Date:October 2015
Completion Date: July 2015

Construction

Start Date: October 2015
Projected Completion Date:March 2017
Completion Date: December 2016

Understand how we build parks.

Funding

Total Funding: $5,454,000
Funding Source:City Council
Design of Marine Park Bocce Court and Sport Court Reconstruction

Location

Marine Park, Brooklyn
Located on the corner of Fillmore Avenue and East 32nd Street in Marine Park.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 03/27/2017

Was this information helpful?