Gertrude Ederle Recreation Center Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install new play equipment at the playground of the Gertrude Ederle Recreation Center.

Project Timeline

Design

Start Date: October 2013
Projected Completion Date: November 2013
Completion Date: October 2015

Procurement

Start Date: October 2015
Projected Completion Date: March 2016
Completion Date: October 2015

Construction

Start Date: May 2016
Projected Completion Date: July 2016
Completion Date: September 2016

Understand how we build parks.

Funding

Total Funding: $803,000
Funding Source: City Council

Location

Gertrude Ederle Recreation Center, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/18/2018