  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct a portion of the playground at Wingate Park and a portion of the playground at Glenwood Playground.

Project Timeline

Design

Start Date: March 2012
Projected Completion Date: April 2012
Completion Date: September 2013

Procurement

Start Date: September 2013
Projected Completion Date: May 2014
Completion Date: July 2014

Construction

Start Date: September 2014
Projected Completion Date: September 2015
Completion Date: May 2016