Dyker Beach Park Paths and Brizzi Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Brizzi Playground and the paths adjacent to Ben Vitale Fields in Dyker Beach Park.

Project Timeline

Design

Start Date: November 2010
Projected Completion Date: April 2012
Completion Date: July 2012

Procurement

Start Date: July 2012
Projected Completion Date: April 2013
Completion Date: October 2013

Construction

Start Date: November 2013
Projected Completion Date: November 2014
Completion Date: November 2014

Understand how we build parks.

Funding

Total Funding: $874,000
Funding Sources:
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/01/2022

Was this information helpful?