Cooper Park Dog Run Construction and Athletic Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball, handball and sand volleyball courts, and construct a dog run in Cooper Park.

Project Timeline

Design

Start Date: March 2012
Projected Completion Date: November 2013
Completion Date: February 2014

Procurement

Start Date: February 2014
Projected Completion Date: November 2014
Completion Date: February 2015

Construction

Start Date: April 2015
Projected Completion Date: April 2016
Completion Date: December 2015

Understand how we build parks.

Funding

Total Funding: $2,459,000
Funding Sources:
  • City Council
  • State

Location

Cooper Park , Brooklyn
Maspeth and Morgan Avenues, Olive and Sharon Streets, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project