Crispus Attucks Playground Handball and Basketball Court Reconstruction

  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    74% complete 

This project will reconstruct the handball and basketball courts in Crispus Attucks Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2012
Projected Completion Date:December 2012
Completion Date: August 2014

Procurement

Start Date: August 2014
Projected Completion Date:May 2015
Completion Date: July 2015

Construction

Start Date: October 2015
Projected Completion Date:January 2017

Understand how we build parks.

Funding

Total Funding: $1,536,000
Funding Source:City Council

Location

Crispus Attucks Playground, Brooklyn
Classon Avenue between Fulton Street and Lefferts Place, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/13/2017