Fort Totten Park Chapel and Commander's House Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the steeple spire and bell tower at the Chapel and reconstruct the roof and exterior woodwork at the Commander's House at Fort Totten.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: August 2011
Projected Completion Date:
May 2013
Completion Date:
September 2015
Procurement
Start Date: September 2015
Projected Completion Date:
June 2016
Completion
Date:
June 2017
Construction
Start Date: September 2017
Projected Completion Date:
March 2019
Completion
Date:
March 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Fort Totten Park
, Queens
Chapel at 423 Abbot Road, Commander's House at 422A Weaver Avenue
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project
Last updated: 08/15/2022