Fort Totten Park Chapel and Commander's House Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    60% complete

This project will reconstruct the steeple spire and bell tower at the Chapel and reconstruct the roof and exterior woodwork at the Commander's House at Fort Totten.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: August 2011
Projected Completion Date: May 2013
Completion Date: September 2015

Procurement

Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: June 2017

Construction

Start Date: September 2017
Projected Completion Date: March 2019
Adjusted Completion Date: May 2020

Understand how we build parks.

Funding

Total Funding: $6,966,000
Funding Source: Mayoral

Location

Fort Totten Park , Queens
Chapel at 423 Abbot Road, Commander's House at 422A Weaver Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 10/18/2019