Fort Totten Park Chapel and Commander's House Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    85% complete

This project will reconstruct the steeple spire and bell tower at the Chapel and reconstruct the roof and exterior woodwork at the Commander's House at Fort Totten.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: August 2011
Projected Completion Date: May 2013
Completion Date: September 2015

Procurement

Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: June 2017

Construction

Start Date: September 2017
Projected Completion Date: March 2019
Adjusted Completion Date: May 2020

Understand how we build parks.

Funding

Total Funding: $6,965,000
Funding Source: Mayoral

Location

Fort Totten Park , Queens
Chapel at 423 Abbot Road, Commander's House at 422A Weaver Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 07/13/2020