Lemon Creek Park Timber Barrier Rail Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct timber barrier rail damaged from Hurricane Sandy at Lemon Creek Park.
Project Timeline
Design
Start Date: March 2015
Projected Completion Date:
September 2015
Completion Date:
August 2015
Procurement
Start Date: February 2016
Projected Completion Date:
July 2016
Completion
Date:
February 2016
Construction
Start Date: May 2016
Projected Completion Date:
August 2016
Completion
Date:
August 2016
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Federal
Location
Lemon Creek Park
, Staten Island
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 07/01/2022