Lemon Creek Park Timber Barrier Rail Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct timber barrier rail damaged from Hurricane Sandy at Lemon Creek Park.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: September 2015
Completion Date: August 2015

Procurement

Start Date: February 2016
Projected Completion Date: July 2016
Completion Date: February 2016

Construction

Start Date: May 2016
Projected Completion Date: August 2016
Completion Date: August 2016

Understand how we build parks.

Funding

Total Funding: $74,000
Funding Sources:
  • Mayoral
  • Federal

Location

Lemon Creek Park, Staten Island

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 11/16/2017