NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Lemon Creek Park Timber Barrier Rail Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct timber barrier rail damaged from Hurricane Sandy at Lemon Creek Park.

Project Timeline


Start Date: March 2015
Projected Completion Date: September 2015
Completion Date: August 2015


Start Date: February 2016
Projected Completion Date: July 2016
Completion Date: February 2016


Start Date: May 2016
Projected Completion Date: August 2016
Completion Date: August 2016

Understand how we build parks.


Total Funding: $87,000
Funding Sources:
  • Mayoral
  • Federal


Lemon Creek Park , Staten Island


Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 03/16/2018

Was this information helpful?