Cross Island Parkway Waters Edge Drive Comfort Station Construction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a comfort station next to the Cross Island Parkway near Waters Edge Drive.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: April 2022

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Cross Island Parkway , Queens
24th Avenue and Waters Edge Drive

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 08/12/2022

Was this information helpful?