Litchfield Villa Telecommunications Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install new telecommunications equipment at Litchfield Villa in Prospect Park.

Project Timeline

Design

Start Date: March 2014
Projected Completion Date: March 2015
Completion Date: March 2015

Procurement

Start Date: April 2015
Projected Completion Date: September 2015
Completion Date: April 2015

Construction

Start Date: May 2015
Projected Completion Date: June 2015
Completion Date: June 2015

Understand how we build parks.

Funding

Total Funding: $100,000
Funding Source: Mayoral

Location

Prospect Park , Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 04/20/2021