Nautilus Playground Sports Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball and handball courts at Nautilus Playground.

Project Timeline

Design

Start Date: February 2014
Projected Completion Date: February 2015
Completion Date: February 2015

Procurement

Start Date: June 2015
Projected Completion Date: November 2015
Completion Date: June 2015

Construction

Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: June 2016

Understand how we build parks.

Funding

Total Funding: $218,000
Funding Source: Mayoral

Location

Nautilus Playground , Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project