Pelham Fritz Recreation Center Boiler Repair

  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    84% complete 

This contract will reconstruct the boilers and heating systems at the Pelham Fritz Recreation Center.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: February 2012
Projected Completion Date:July 2012
Completion Date: August 2013

Procurement

Start Date: August 2013
Projected Completion Date:May 2014
Completion Date: December 2014

Construction

Start Date: February 2015
Projected Completion Date:February 2016
Adjusted Completion Date: December 2016

Understand how we build parks.

Funding

Total Funding: $667,000
Funding Sources:
  • Mayor
  • City Council

Location

Marcus Garvey Park, Manhattan
Mount Morris Park West and West 122nd Street, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/13/2017