PO Jeff Herman Ballfield Reconstruction

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a track and synthetic turf field at PO Jeff Herman Ballfield.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The schematic design for this project has been approved. Parks is now developing the documents required to build this project.

Project Timeline

Design

Start Date: December 2021
Projected Completion Date: December 2022

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: City Council

Location

McDonald Playground , Brooklyn
McDonald Avenue between Avenues S & T

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/01/2022