NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Oakridge Turn/Forest Park Drive Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the sidewalks, guardrails, curbs and crosswalks at Oakridge Turn in Forest Park.

Project Timeline

Design

Start Date: May 2015
Projected Completion Date: August 2015
Completion Date: October 2015

Procurement

Start Date: April 2016
Projected Completion Date: September 2016
Completion Date: September 2016

Construction

Start Date: April 2017
Projected Completion Date: August 2017
Completion Date: September 2017

Understand how we build parks.

Funding

Total Funding: $39,000
Funding Source: Mayoral

Location

Forest Park, Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/20/2017

Was this information helpful?