Oakridge Turn/Forest Park Drive Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the sidewalks, guardrails, curbs and crosswalks at Oakridge Turn in Forest Park.

Project Timeline


Start Date: May 2015
Projected Completion Date: August 2015
Completion Date: October 2015


Start Date: April 2016
Projected Completion Date: September 2016
Completion Date: September 2016


Start Date: April 2017
Projected Completion Date: August 2017
Completion Date: September 2017

Understand how we build parks.


Total Funding: $39,000
Funding Source: Mayoral


Forest Park , Queens


Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 03/16/2018