Riverside Park South West 69th Street Transfer Bridge Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will stabilize and restore existing structures with historically appropriate materials at Riverside Park South. This project will also include lead abatement activities, adding lighting on gantry towers, providing interpretive signage at ground level and removing 65 additional piles at Pier F.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: December 2016
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: February 2020
Adjusted Completion Date: December 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • Federal
  • Private

Location

Riverside Park South , Manhattan
Hudson River at West 69th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/28/2020