NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Riverside Park West 69th Street Transfer Bridge Reconstruction

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will stabilize and restore existing structures with historically appropriate materials. This project will also include lead abatement activities, adding lighting on gantry towers, providing interpretive signage at ground level and removing 65 additional piles at Pier F.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: December 2016
Adjusted Completion Date: July 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • Federal
  • Private

Location

Riverside Park South , Manhattan
Hudson River at West 69th Street and Riverside Park South, Borough of Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 05/24/2018

Was this information helpful?