Bronx Street Tree Planting FY21 - Community Boards 9-12
-
100% complete
-
100% complete
-
0% complete
This project will plant new trees in Community Boards 9-12 in the Bronx.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: May 2021
Projected Completion Date:
September 2021
Completion Date:
May 2021
Procurement
Start Date: May 2021
Projected Completion Date:
February 2022
Completion
Date:
November 2021
Construction
Start Date: August 2021
Projected Completion Date:
August 2022
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Private
Last updated: 08/10/2022