Bronx Street Tree Planting FY21 - Community Boards 9-12

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will plant new trees in Community Boards 9-12 in the Bronx.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: May 2021
Projected Completion Date: September 2021
Completion Date: May 2021

Procurement

Start Date: May 2021
Projected Completion Date: February 2022
Completion Date: November 2021

Construction

Start Date: August 2021
Projected Completion Date: August 2022

Understand how we build parks.

Funding

Total Funding: $2,670,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations in the Bronx

Project Staff

Contact NYC Parks about this project

Last updated: 08/10/2022

Was this information helpful?